Panel Upgrades in Vancouver: How Long, How Loud, How Much? (Homeowner Q&A)

This 2026 homeowner Q&A explains what to expect when upgrading an electrical panel or service in the City of Vancouver. It covers typical timelines, noise and disruption, cost drivers, permits and inspections, and how BC Hydro and Technical Safety BC guidance factor into your project.


Quick answer:

  • Most panel changeouts take 1 day onsite, with the main power off for 2 to 6 hours. Service upgrades that involve BC Hydro coordination or trenching can span 1 to 3 weeks end-to-end depending on scheduling.

  • Noise is comparable to a short indoor renovation: drilling, fastening, and meter work. Exterior work can include coring or trenching if you convert to underground.

  • Cost depends on service size, meter location, overhead vs underground, breaker count, and finish repairs. A formal load calculation prevents over-scoping and helps you choose 100 A, 125 A, 150 A, or 200 A.

  • Inside Vancouver, the City issues electrical permits and performs inspections. Technical Safety BC bulletins frame how services and equipment must comply with the 2024 BC Electrical Code.


👉 Get a right-sized plan and quote

👉 Confirm capacity before you commit

At-a-glance: timeline, noise, and cost drivers

Topic

What to expect

Why it varies

How to keep it smooth

How long

Panel-only swaps: 1 day onsite. Service upgrades: utility coordination can make total timeline 1–3 weeks

BC Hydro scheduling, meter relocation, overhead vs underground, inspections

Approve designs early, book BC Hydro and inspection windows in advance

How loud

Interior drilling and fastening; exterior coring or trenching if underground

Wall type, meter location, underground conversion

Protect valuables, plan for pets, notify neighbors and strata if needed

How much

Pricing scales with service size, meter move, underground work, breaker count, AFCI/GFCI upgrades, surge device

Equipment specs, finish repairs, civil work

Use a load calc to avoid oversizing; reuse viable pathways; combine projects in one permit

Power off

Typically 2–6 hours on upgrade day

Scope and inspection timing

Schedule refrigerators, work-from-home, and medical devices accordingly

Permits & inspections

City of Vancouver electrical permit, rough-in and final inspections

Meter moves or service changes may add utility steps

Provide panel schedules, labels, and as-builts for fast sign-off

Who qualifies in 2026

  • Detached homes, duplexes, and row homes within the City of Vancouver needing added capacity for EV chargers, heat pumps, suites, or kitchen/laundry circuits.

  • Owners replacing aging or crowded panels for safety or insurance.

  • Properties converting from overhead to underground service or relocating the meter for access compliance.

Dates, deadlines, and coordination tips

  • Apply for the City of Vancouver electrical permit before work begins and keep inspection records with your home files.

  • If your upgrade includes a meter relocation or an overhead-to-underground conversion, coordinate with BC Hydro’s service connection team for trench, conduit, and clearance standards.

  • Label the new panel with service rating and an updated panel schedule. Inspectors will check labels, AFCI/GFCI protection, and equipment listings.

Stacking and special cases

  • EV load management vs upsizing. If the load calculation is borderline, an EV Energy Management System can often keep a 100 A or 125 A service viable. Revisit 200 A when you add a second EV or a heat pump.

  • Secondary suites. Suites can trigger additional requirements for smoke and CO alarms, GFCI/AFCI protection, and sometimes metering changes.

  • Heritage and tight lots. Mandatory exterior meter access can require wall repairs or screens that still meet clearance rules. Budget a small allowance for finishes.

How to proceed in 3 steps

For homeowners

  1. Start with a load calculation and site review to choose the right service size and confirm if underground conversion is required.

    Load Calculations and Capacity Assessments

  2. Lock the scope: panel rating, meter location, overhead vs underground route, and any EV or renovation circuits to include now.

    Service and Panel Upgrades

  3. Permit, install, and inspect. Expect a single-day outage window and keep inspection approvals for insurance and resale.

Frequently asked questions

How much does a typical panel upgrade cost in Vancouver

Budgets scale with service size and civil work. A panel-only change with similar location is the least expensive. Moving the meter or converting to underground adds conduit, coring, or trenching and can be the largest single cost driver. The fastest way to tighten numbers is to run a load calculation and confirm the meter location early.

How long will my power be off

Most panel or service upgrades require 2 to 6 hours without power on the installation day. If BC Hydro work is needed at the service point, the outage window is scheduled in advance.

Will it be noisy

Inside work is similar to other small renos: drilling and fastening. Exterior coring or trenching is noisier and may require brief access to side yards or driveways. Let neighbors or strata know your upgrade date.

Do I need a City of Vancouver permit

Yes. Panel and service upgrades inside city limits require a City electrical permit and inspections. Keep the permit number and approval documents with your home records.

What about Technical Safety BC if the City issues my permit

Technical Safety BC publishes bulletins and interpretations that frame how services and equipment must comply with the 2024 BC Electrical Code. Your installation still needs to meet those requirements, which the City applies during inspection.

Can load management let me avoid a 200 A upgrade

Often yes. If the load calculation shows you are close to the limit, EV load management can keep a 100 A or 125 A service compliant while you charge overnight.

Do I need to coordinate with BC Hydro

Only when the service point or meter base changes, or when converting to underground. Your contractor will book the utility work and follow BC Hydro’s trenching and clearance standards.

Make it easy with Akai Electric

We design and install code-compliant panel and service upgrades across Vancouver. From sizing and metering to trenching and inspections, we handle the details so you get capacity without surprises.

Get a same-week assessment

Add EV capacity the smart way

Sources

Topic or claim

Official source

City of Vancouver electrical permits and inspections for work inside city limits

City of Vancouver development and building–related fees schedule

Technical Safety BC bulletin framing services and service equipment under the 2024 BC Electrical Code

Technical Safety BC electrical installation permits and process context

BC Hydro service connection standards and trenching guidance for overhead and underground


 
 
 